Switchgear MCQs — Set 4

10 practice questions on instrument transformers and busbars — CTs, PTs, busbar materials and busbar arrangements, with answers and explanations.

Q1. What is the purpose of a current transformer (CT) in switchgear?

  • (a) To step down current for metering and protection
  • (b) To step up voltage
  • (c) To interrupt fault current
  • (d) To store energy

Answer: (a) To step down current for metering and protection — a CT turns, say, 400 A into 5 A so meters and relays can handle it safely.

Q2. The standard secondary current of a CT is:

  • (a) 110 A
  • (b) 5 A (or 1 A)
  • (c) 100 A
  • (d) 0.5 A

Answer: (b) 5 A (or 1 A) — standard CT secondaries are 5 A or 1 A, feeding meters and protective relays.

Q3. Why must a CT secondary never be left open-circuited while the primary is energised?

  • (a) The meter would read zero only
  • (b) Dangerously high voltage is induced in the secondary and the core saturates
  • (c) The breaker would trip
  • (d) The busbar would overheat

Answer: (b) Dangerously high voltage is induced in the secondary and the core saturates — an open CT secondary can produce thousands of volts and is a serious shock and insulation hazard.

Q4. The standard secondary voltage of a potential transformer (PT/VT) is:

  • (a) 230 V
  • (b) 110 V
  • (c) 11 kV
  • (d) 5 V

Answer: (b) 110 V — a PT steps the line voltage down to 110 V for meters, relays and synchronising equipment.

Q5. What is the function of a busbar in switchgear?

  • (a) To interrupt faults
  • (b) To act as a common conductor distributing power to several outgoing circuits
  • (c) To measure voltage
  • (d) To earth the system

Answer: (b) To act as a common conductor distributing power to several outgoing circuits — incoming and outgoing feeders all connect to the busbar.

Q6. Busbars are usually made of:

  • (a) Steel only
  • (b) Copper or aluminium
  • (c) Plastic
  • (d) Lead

Answer: (b) Copper or aluminium — both have high conductivity; copper is used where space is tight, aluminium where cost and weight matter.

Q7. Which CT accuracy class is used for protection purposes?

  • (a) Class 0.2
  • (b) Class 5P
  • (c) Class 1.0
  • (d) Class 0.5

Answer: (b) Class 5P — 5P class CTs (for example 5P10 or 5P20) are for protection; classes 0.2, 0.5 and 1.0 are metering classes.

Q8. A PT is connected in a circuit:

  • (a) In series with the load
  • (b) In parallel (across the line)
  • (c) In series with the CT
  • (d) Across the breaker contacts

Answer: (b) In parallel (across the line) — a PT measures voltage, so it connects across the conductors, unlike a CT which is in series.

Q9. What is the main disadvantage of a single-busbar arrangement?

  • (a) It is too expensive
  • (b) The whole substation must shut down for busbar maintenance
  • (c) It cannot carry load current
  • (d) It needs two breakers per circuit

Answer: (b) The whole substation must shut down for busbar maintenance — with only one bus there is no alternative path for the supply.

Q10. What is the main advantage of a double-busbar arrangement?

  • (a) Lower cost than a single busbar
  • (b) Load can be transferred between buses, so maintenance is possible without interrupting supply
  • (c) It needs no isolators
  • (d) It eliminates short circuits

Answer: (b) Load can be transferred between buses, so maintenance is possible without interrupting supply — any circuit can be moved to the healthy bus.