Electrical Drawing Symbols MCQs — Set 9
10 practice questions on as-built drawings, drawing standards and the common mistakes that make drawings useless.
Q1. What is an as-built drawing?
- (a) A drawing made before the work starts
- (b) A drawing updated to record exactly what was actually installed on site
- (c) A drawing of the building’s structure only
- (d) A drawing that is never used again
Answer: (b) A drawing updated to record exactly what was actually installed on site — it is the true record handed over to the owner.
Q2. Which international standard defines the graphical symbols used in electrical diagrams?
- (a) IEC 60617
- (b) ISO 9001
- (c) IEC 60364
- (d) IS 732
Answer: (a) IEC 60617 — it is the standard collection of graphical symbols for electrical diagrams.
Q3. What is the most common mistake when drawing electrical symbols by hand?
- (a) Using non-standard, made-up symbols that other people cannot understand
- (b) Drawing the symbols too neatly
- (c) Using a ruler
- (d) Labelling every symbol
Answer: (a) Using non-standard, made-up symbols that other people cannot understand — a drawing only works if everyone reads the same symbols.
Q4. What happens if a drawing has no legend and uses unusual symbols?
- (a) Nothing — the electrician will guess correctly
- (b) The drawing can be misread, causing wrong wiring, rework and safety risks
- (c) The drawing becomes cheaper to print
- (d) The drawing is automatically approved
Answer: (b) The drawing can be misread, causing wrong wiring, rework and safety risks — the legend is what makes an unfamiliar symbol readable.
Q5. A circuit is changed on site but the drawing is not updated. What is the result?
- (a) No problem at all
- (b) Future fault-finding and additions will follow a wrong drawing and may cause danger
- (c) The circuit will stop working immediately
- (d) The drawing becomes more valuable
Answer: (b) Future fault-finding and additions will follow a wrong drawing and may cause danger — the drawing must always match what is actually installed.
Q6. What does an approval stamp on a drawing mean?
- (a) The drawing has been checked and approved for use
- (b) The drawing is only a rough sketch
- (c) The drawing is out of date
- (d) The drawing belongs to the client
Answer: (a) The drawing has been checked and approved for use — only approved drawings should be used for construction.
Q7. What is the difference between a “for tender” drawing and a “for construction” drawing?
- (a) A tender drawing is used for pricing the job; a construction drawing is the final approved version for building
- (b) A tender drawing is always in colour
- (c) A construction drawing has no dimensions
- (d) There is no difference
Answer: (a) A tender drawing is used for pricing the job; a construction drawing is the final approved version for building — work must only start from the construction issue.
Q8. A socket is drawn on the wrong wall of a room. What is the most likely consequence?
- (a) The socket will work better
- (b) The socket is fixed in the wrong place and must be moved, costing time and money
- (c) The circuit breaker will trip
- (d) The voltage will drop
Answer: (b) The socket is fixed in the wrong place and must be moved, costing time and money — one wrong symbol position on paper becomes real rework on site.
Q9. Which of these must always match between the drawing and the actual installation?
- (a) The colour of the paper
- (b) The cable sizes, routes and breaker ratings
- (c) The name of the drawing software
- (d) The number of pages
Answer: (b) The cable sizes, routes and breaker ratings — these decide safety and performance, so they must agree with the real work.
Q10. On a 1:100 scale drawing, a wall measures 2.5 cm on paper. What is its real length?
- (a) 1.25 m
- (b) 2.5 m
- (c) 5 m
- (d) 25 m
Answer: (b) 2.5 m — at 1:100, 1 cm on paper = 100 cm = 1 m, so 2.5 cm = 2.5 m.