Charge Controller MCQs — Set 5

10 practice questions on matching a charge controller to the battery voltage — 12 V, 24 V and 48 V systems, and charging-time sums. Work each one out before checking the answer.

Q1. A 300 W solar array charges a 24 V battery. What is the charging current?

  • (a) 25 A
  • (b) 12.5 A
  • (c) 6.25 A
  • (d) 300 A

Answer: (b) 12.5 A — I = P ÷ V = 300 ÷ 24 = 12.5 A. On a 12 V battery the same 300 W would be 25 A, so a 24 V system halves the current.

Q2. How does an auto-detecting charge controller learn whether the system is 12 V or 24 V?

  • (a) From the solar panel label
  • (b) From the battery voltage when the battery is connected first
  • (c) From the load terminals
  • (d) It guesses at random each morning

Answer: (b) From the battery voltage when the battery is connected first — this is another reason the battery must be connected before the panels.

Q3. Why are larger off-grid systems often built at 48 V instead of 12 V?

  • (a) 48 V batteries are cheaper per amp-hour
  • (b) Higher voltage means lower current for the same power, so thinner cables and smaller losses
  • (c) 48 V panels produce more sunlight
  • (d) Charge controllers only work at 48 V

Answer: (b) Higher voltage means lower current for the same power, so thinner cables and smaller losses — at 48 V a 1,000 W load draws only about 21 A instead of 83 A at 12 V.

Q4. Can a single 12 V (nominal) solar panel properly charge a 24 V battery bank?

  • (a) Yes, any panel charges any battery
  • (b) No — the panel voltage is too low to reach the 24 V battery’s charging voltage
  • (c) Yes, but only with a PWM controller
  • (d) Yes, if the panel is connected in the evening

Answer: (b) No — the panel voltage is too low to reach the 24 V battery’s charging voltage — panels must be wired in series (or a higher-voltage panel used) to charge a 24 V bank.

Q5. A 100 Ah battery is charged at 10 A. About how long will a full charge take, allowing for charging losses?

  • (a) 7 hours
  • (b) 10 hours
  • (c) 14 hours
  • (d) 20 hours

Answer: (c) 14 hours — time = Ah ÷ A × 1.4 = 100 ÷ 10 × 1.4 = 14 h.

Q6. A 100 Ah battery is half discharged (50 Ah used). It is charged at 10 A. About how long until it is full?

  • (a) 3.5 hours
  • (b) 7 hours
  • (c) 14 hours
  • (d) 5 hours

Answer: (b) 7 hours — time = 50 ÷ 10 × 1.4 = 7 h; only the 50 Ah that was used needs replacing.

Q7. A 10 A DC load runs for 5 hours each night from a battery bank. If the bank must not be discharged below 50%, what size battery bank is needed?

  • (a) 25 Ah
  • (b) 50 Ah
  • (c) 100 Ah
  • (d) 200 Ah

Answer: (c) 100 Ah — the load uses 10 × 5 = 50 Ah per night; at a 50% depth of discharge the bank must be twice that, 50 ÷ 0.5 = 100 Ah.

Q8. The charge controller’s battery-type setting is set to 24 V while the battery bank is actually 12 V. What happens?

  • (a) The battery charges normally
  • (b) The controller applies 24 V charging voltages to a 12 V battery, overcharging and damaging it
  • (c) The panels produce half power
  • (d) Nothing — the setting is only a label

Answer: (b) The controller applies 24 V charging voltages to a 12 V battery, overcharging and damaging it — the voltage setting must always match the actual battery bank.

Q9. A 1,000 W solar array charges a 48 V battery bank. Roughly what is the charging current?

  • (a) 48 A
  • (b) 20.8 A
  • (c) 83.3 A
  • (d) 10.4 A

Answer: (b) 20.8 A — I = P ÷ V = 1,000 ÷ 48 = 20.8 A.

Q10. Two 12 V batteries are wired in series. What system voltage does the charge controller see?

  • (a) 6 V
  • (b) 12 V
  • (c) 24 V
  • (d) 48 V

Answer: (c) 24 V — batteries in series add voltage (12 + 12 = 24 V) while the amp-hour capacity stays the same.