Q1. What does N+1 redundancy mean in a UPS system?

  • (a) One UPS module more than the minimum needed, so the load stays protected if one module fails
  • (b) One battery more than the load needs
  • (c) One extra mains supply only
  • (d) One UPS for every load

Answer: (a) One UPS module more than the minimum needed, so the load stays protected if one module fails — redundancy removes the single point of failure.

Q2. When is a three-phase UPS used instead of a single-phase UPS?

  • (a) For small home computers
  • (b) For large loads such as data centres and industrial sites that run on three-phase supply
  • (c) For battery charging only
  • (d) Three-phase UPS units do not exist

Answer: (b) For large loads such as data centres and industrial sites that run on three-phase supply — single-phase UPS units cannot serve large three-phase loads.

Q3. What is eco mode in a UPS?

  • (a) A mode that switches the UPS off completely
  • (b) A high-efficiency mode where the load runs from the mains and the inverter only takes over if the mains fails or goes out of range
  • (c) A mode that uses solar power only
  • (d) A mode that doubles the battery size

Answer: (b) A high-efficiency mode where the load runs from the mains and the inverter only takes over if the mains fails or goes out of range — it saves energy but adds a small transfer time.

Q4. What is a cold start on a UPS?

  • (a) Starting the UPS from its battery when there is no mains power at all
  • (b) Starting the UPS in a cold room
  • (c) Switching the UPS on for the first time ever
  • (d) Cooling the UPS down after an overload

Answer: (a) Starting the UPS from its battery when there is no mains power at all — useful to power a load briefly during a blackout even before mains returns.

Q5. What does UPS monitoring software (for example over USB or SNMP) let you do?

  • (a) Shut down computers automatically before the battery runs out
  • (b) Increase the battery capacity
  • (c) Change the mains voltage
  • (d) Replace the battery remotely

Answer: (a) Shut down computers automatically before the battery runs out — monitoring software triggers a graceful shutdown when runtime gets low.

Q6. A load draws 750 W at a power factor of 0.75. What UPS rating in VA is needed?

  • (a) 563 VA
  • (b) 750 VA
  • (c) 1,000 VA
  • (d) 1,250 VA

Answer: (c) 1,000 VA — VA = 750 ÷ 0.75 = 1,000 VA.

Q7. A UPS has a 12 V, 65 Ah battery and powers a 130 W load. What is the runtime at 80% usable capacity?

  • (a) 2.4 hours
  • (b) 3.2 hours
  • (c) 4.8 hours
  • (d) 6 hours

Answer: (c) 4.8 hours — battery energy = 12 × 65 = 780 Wh; ideal runtime = 780 ÷ 130 = 6 h; at 80% = 4.8 h.

Q8. Why does UPS runtime fall as the battery gets older?

  • (a) The battery’s capacity fades with age and charge cycles, so it stores less energy
  • (b) The load gets heavier with age
  • (c) The mains voltage rises with age
  • (d) Old batteries charge faster and hold more

Answer: (a) The battery’s capacity fades with age and charge cycles, so it stores less energy — a 5-year-old battery may hold only half its original capacity.

Q9. A 70 Ah UPS battery is charged at 10 A. Roughly how long will a full charge take, allowing for charging losses?

  • (a) 7 hours
  • (b) 9.8 hours
  • (c) 14 hours
  • (d) 20 hours

Answer: (b) 9.8 hours — charging time = 70 ÷ 10 × 1.4 = 7 × 1.4 = 9.8 hours.

Q10. A hospital operating theatre and a home PC both need backup power. Which statement is correct?

  • (a) Both can safely use the same small standby UPS
  • (b) The hospital needs an online double-conversion UPS (with generator backup), while the home PC is fine on a small standby UPS
  • (c) The hospital needs no UPS at all
  • (d) The home PC needs a three-phase UPS

Answer: (b) The hospital needs an online double-conversion UPS (with generator backup), while the home PC is fine on a small standby UPS — critical life-safety loads need zero transfer time and long backup; a PC does not.