Q1. What information must a test certificate record?

  • (a) Only the installer’s name
  • (b) The measured test results, the date, the circuits tested and the name of the tester
  • (c) Only the cost of the materials
  • (d) Only the address of the building

Answer: (b) The measured test results, the date, the circuits tested and the name of the tester — a certificate without readings and a responsible signature proves nothing.

Q2. Why are test records kept after the job is finished?

  • (a) To fill the filing cabinet
  • (b) As proof the installation was tested and safe, and as a baseline for future fault-finding
  • (c) To impress visitors
  • (d) They are not kept — they are thrown away at handover

Answer: (b) As proof the installation was tested and safe, and as a baseline for future fault-finding — later testers compare new readings with the originals to spot deterioration.

Q3. What is a periodic inspection and test of an existing installation?

  • (a) A test done only when the building is sold
  • (b) A test done only after a fire
  • (c) A re-test of the installation at set intervals to check it is still safe after years of use
  • (d) A test of the electricity meter only

Answer: (c) A re-test of the installation at set intervals to check it is still safe after years of use — insulation ages, connections loosen and loads change, so safety must be re-proven over time.

Q4. What is the schedule of test results?

  • (a) A timetable for the installer
  • (b) A price list for the materials
  • (c) A delivery schedule for cable
  • (d) A table listing the measured value for every circuit tested, such as Zs and insulation resistance

Answer: (d) A table listing the measured value for every circuit tested, such as Zs and insulation resistance — it accompanies the certificate so every reading can be checked against the limits.

Q5. A circuit fails its insulation resistance test. What is the correct action?

  • (a) Energise it anyway and see what happens
  • (b) Ignore the result and sign the certificate
  • (c) Write the failed value down as a pass
  • (d) Find and fix the fault, then retest until the circuit passes

Answer: (d) Find and fix the fault, then retest until the circuit passes — a failed test means the circuit is not safe, and no certificate can be issued for it until it passes.

Q6. Which set of rules governs how electrical installations are tested and what limits apply?

  • (a) The installer’s personal preference
  • (b) The national wiring regulations, such as BS 7671 or the NEC
  • (c) The cable manufacturer’s advertising
  • (d) The client’s wishes alone

Answer: (b) The national wiring regulations, such as BS 7671 or the NEC — the test limits (for example IR above 1 MΩ) and the test methods come from the wiring regulations, not from guesswork.

Q7. What is an EICR?

  • (a) An Electrical Installation Condition Report, recording the condition of an existing installation after periodic inspection and testing
  • (b) A certificate for a brand-new cable only
  • (c) A receipt for the test instrument
  • (d) A licence to sell electricity

Answer: (a) An Electrical Installation Condition Report, recording the condition of an existing installation after periodic inspection and testing — it lists any defects found and whether the installation is satisfactory for continued use.

Q8. What is a Minor Works Certificate used for?

  • (a) A complete new installation
  • (b) A whole building rewire
  • (c) A factory installation
  • (d) A small addition or alteration, such as adding one socket to an existing circuit

Answer: (d) A small addition or alteration, such as adding one socket to an existing circuit — minor works get their own shorter certificate covering the circuits that were changed and tested.

Q9. How is a measured test result judged as a pass or a fail?

  • (a) By comparing it with the standard limits, for example insulation resistance above 1 MΩ or RCD trip within 300 ms
  • (b) By guessing from the age of the cable
  • (c) By asking the client
  • (d) By the colour of the test leads

Answer: (a) By comparing it with the standard limits, for example insulation resistance above 1 MΩ or RCD trip within 300 ms — every test has a pass limit in the regulations, and the reading is judged against it.

Q10. Who should keep a copy of the completed test certificate?

  • (a) Nobody — it is thrown away
  • (b) The client or building owner, with a copy kept by the installer
  • (c) Only the electricity supplier
  • (d) Only the cable manufacturer

Answer: (b) The client or building owner, with a copy kept by the installer — the owner needs it as proof of safety and for future work, and the installer keeps a copy for their own records.