Testing and Commissioning MCQs — Set 8

10 practice questions on the commissioning sequence — the order of testing, energising, and handing the installation over to the client.

Q1. What is the correct order of work when commissioning a new installation?

  • (a) Visual inspection, then dead tests, then live tests, then functional tests, then energise
  • (b) Energise first, then test if anything trips
  • (c) Functional tests first, then visual inspection
  • (d) Live tests first, then dead tests

Answer: (a) Visual inspection, then dead tests, then live tests, then functional tests, then energise — each stage proves the installation is safe before the next, riskier stage begins.

Q2. Why is a visual inspection done before any instrument test?

  • (a) It is the quickest part of the job
  • (b) It replaces the need for testing
  • (c) It can reveal damage, wrong components, missing covers or loose connections before power is anywhere near the circuit
  • (d) It is only done for the photograph

Answer: (c) It can reveal damage, wrong components, missing covers or loose connections before power is anywhere near the circuit — an obvious defect found by eye should be fixed before any meter is connected.

Q3. When energising a new installation, how should the circuits be switched on?

  • (a) All at once, as fast as possible
  • (b) One circuit at a time, checking each one as it is energised
  • (c) Only the lighting circuits, never the sockets
  • (d) Only after the client has moved in

Answer: (b) One circuit at a time, checking each one as it is energised — switching on one circuit at a time means a fault is traced to the circuit just energised instead of the whole installation.

Q4. Which documents should be handed to the client at handover?

  • (a) Only the electricity bill
  • (b) Only the cable invoice
  • (c) Only the installer’s business card
  • (d) Test certificates, as-built drawings and equipment manuals

Answer: (d) Test certificates, as-built drawings and equipment manuals — the client needs proof the installation was tested, drawings showing what was actually built, and manuals for the equipment installed.

Q5. What is a snag list in commissioning?

  • (a) A list of tools used on the job
  • (b) A list of defects or unfinished items that must be fixed before handover
  • (c) A list of cable colours
  • (d) A list of future jobs

Answer: (b) A list of defects or unfinished items that must be fixed before handover — snags are noted during inspection and testing, then cleared one by one until none remain.

Q6. Who signs the test certificate for an installation?

  • (a) The person who delivered the cable
  • (b) The building owner, without checking anything
  • (c) The competent person who carried out the testing and is responsible for the results
  • (d) Any visitor to the site

Answer: (c) The competent person who carried out the testing and is responsible for the results — the signature is a declaration that the installation has been tested and is safe.

Q7. Why should the installer demonstrate the system to the client at handover?

  • (a) To show off the new tools
  • (b) So the client knows how to operate the system, reset an RCD and find the distribution board
  • (c) To charge extra for the visit
  • (d) To use up the remaining cable

Answer: (b) So the client knows how to operate the system, reset an RCD and find the distribution board — a client who understands the installation can use it safely and act correctly when something trips.

Q8. Why are “as-built” drawings kept after commissioning?

  • (a) They are needed for future maintenance, fault-finding and additions
  • (b) They make the walls look better
  • (c) They are required to sell the cable
  • (d) They are only kept for one week

Answer: (a) They are needed for future maintenance, fault-finding and additions — as-built drawings show what was actually installed, including cable routes and circuit details, which the original plans may not match.

Q9. When commissioning a distribution board, what should be checked?

  • (a) Only the colour of the board
  • (b) That every circuit is labelled, terminals are tight, and the correct breakers are fitted
  • (c) Only the size of the board
  • (d) Only the number of spare ways

Answer: (b) That every circuit is labelled, terminals are tight, and the correct breakers are fitted — a board with wrong breakers, loose terminals or no labels is not ready for handover.

Q10. What is the final step before an installation is handed over to the client?

  • (a) Switching everything off and leaving
  • (b) Confirming all tests have passed, defects are cleared, and the certificate is issued
  • (c) Removing all labels from the board
  • (d) Throwing away the test results

Answer: (b) Confirming all tests have passed, defects are cleared, and the certificate is issued — handover only happens when the installation is proven safe and the paperwork is complete.