Testing and Commissioning MCQs — Set 8
10 practice questions on the commissioning sequence — the order of testing, energising, and handing the installation over to the client.
Q1. What is the correct order of work when commissioning a new installation?
- (a) Visual inspection, then dead tests, then live tests, then functional tests, then energise
- (b) Energise first, then test if anything trips
- (c) Functional tests first, then visual inspection
- (d) Live tests first, then dead tests
Answer: (a) Visual inspection, then dead tests, then live tests, then functional tests, then energise — each stage proves the installation is safe before the next, riskier stage begins.
Q2. Why is a visual inspection done before any instrument test?
- (a) It is the quickest part of the job
- (b) It replaces the need for testing
- (c) It can reveal damage, wrong components, missing covers or loose connections before power is anywhere near the circuit
- (d) It is only done for the photograph
Answer: (c) It can reveal damage, wrong components, missing covers or loose connections before power is anywhere near the circuit — an obvious defect found by eye should be fixed before any meter is connected.
Q3. When energising a new installation, how should the circuits be switched on?
- (a) All at once, as fast as possible
- (b) One circuit at a time, checking each one as it is energised
- (c) Only the lighting circuits, never the sockets
- (d) Only after the client has moved in
Answer: (b) One circuit at a time, checking each one as it is energised — switching on one circuit at a time means a fault is traced to the circuit just energised instead of the whole installation.
Q4. Which documents should be handed to the client at handover?
- (a) Only the electricity bill
- (b) Only the cable invoice
- (c) Only the installer’s business card
- (d) Test certificates, as-built drawings and equipment manuals
Answer: (d) Test certificates, as-built drawings and equipment manuals — the client needs proof the installation was tested, drawings showing what was actually built, and manuals for the equipment installed.
Q5. What is a snag list in commissioning?
- (a) A list of tools used on the job
- (b) A list of defects or unfinished items that must be fixed before handover
- (c) A list of cable colours
- (d) A list of future jobs
Answer: (b) A list of defects or unfinished items that must be fixed before handover — snags are noted during inspection and testing, then cleared one by one until none remain.
Q6. Who signs the test certificate for an installation?
- (a) The person who delivered the cable
- (b) The building owner, without checking anything
- (c) The competent person who carried out the testing and is responsible for the results
- (d) Any visitor to the site
Answer: (c) The competent person who carried out the testing and is responsible for the results — the signature is a declaration that the installation has been tested and is safe.
Q7. Why should the installer demonstrate the system to the client at handover?
- (a) To show off the new tools
- (b) So the client knows how to operate the system, reset an RCD and find the distribution board
- (c) To charge extra for the visit
- (d) To use up the remaining cable
Answer: (b) So the client knows how to operate the system, reset an RCD and find the distribution board — a client who understands the installation can use it safely and act correctly when something trips.
Q8. Why are “as-built” drawings kept after commissioning?
- (a) They are needed for future maintenance, fault-finding and additions
- (b) They make the walls look better
- (c) They are required to sell the cable
- (d) They are only kept for one week
Answer: (a) They are needed for future maintenance, fault-finding and additions — as-built drawings show what was actually installed, including cable routes and circuit details, which the original plans may not match.
Q9. When commissioning a distribution board, what should be checked?
- (a) Only the colour of the board
- (b) That every circuit is labelled, terminals are tight, and the correct breakers are fitted
- (c) Only the size of the board
- (d) Only the number of spare ways
Answer: (b) That every circuit is labelled, terminals are tight, and the correct breakers are fitted — a board with wrong breakers, loose terminals or no labels is not ready for handover.
Q10. What is the final step before an installation is handed over to the client?
- (a) Switching everything off and leaving
- (b) Confirming all tests have passed, defects are cleared, and the certificate is issued
- (c) Removing all labels from the board
- (d) Throwing away the test results
Answer: (b) Confirming all tests have passed, defects are cleared, and the certificate is issued — handover only happens when the installation is proven safe and the paperwork is complete.