Testing and Commissioning MCQs — Set 1

10 practice questions on why electrical testing matters and what to check before a circuit is energised, with answers and explanations.

Q1. Why must a new circuit be tested before it is switched on for the first time?

  • (a) To make the installation look neat
  • (b) To find hidden faults before they cause damage, shock or fire
  • (c) To use up spare cable
  • (d) To check the colour of the wires

Answer: (b) To find hidden faults before they cause damage, shock or fire — testing catches faults such as damaged insulation or wrong connections while the circuit is still safe to fix.

Q2. What is a “dead test”?

  • (a) A test carried out with the supply isolated and proved dead
  • (b) A test carried out at full load
  • (c) A test carried out on a switched-off appliance only
  • (d) A test that needs no instrument

Answer: (a) A test carried out with the supply isolated and proved dead — continuity, insulation resistance and polarity tests are all dead tests.

Q3. What is the first step before carrying out any test on an installation?

  • (a) Switch everything on
  • (b) Connect the test instrument to the live terminals
  • (c) Isolate the supply, lock it off and prove it dead
  • (d) Fill in the test certificate

Answer: (c) Isolate the supply, lock it off and prove it dead — no test is safe to start until the circuit cannot be energised by mistake.

Q4. Which test would reveal a short circuit between the live and neutral conductors of a new cable run?

  • (a) A visual inspection only
  • (b) A load test
  • (c) A polarity test
  • (d) An insulation resistance test

Answer: (d) An insulation resistance test — a very low resistance reading between live and neutral shows the insulation has failed or the conductors are touching.

Q5. Who or what does dead testing protect?

  • (a) The installer, the user and the equipment
  • (b) Only the electricity meter
  • (c) Only the cable manufacturer
  • (d) Only the test instrument

Answer: (a) The installer, the user and the equipment — faults found while the circuit is dead can be fixed without the risk of shock, arc flash or burnt-out equipment.

Q6. What does “commissioning” an electrical installation mean?

  • (a) Buying the materials for the job
  • (b) Checking, testing and energising the installation to confirm it works as designed
  • (c) Painting the distribution board
  • (d) Disconnecting the supply for maintenance

Answer: (b) Checking, testing and energising the installation to confirm it works as designed — commissioning is the final proof that the installation is safe and ready for use.

Q7. A circuit looks correctly wired, with no visible damage. Why should it still be tested?

  • (a) Because the cable colour may fade
  • (b) Because testing is only done for old installations
  • (c) Because hidden faults such as nicked insulation or a loose connection cannot be seen
  • (d) Because the client asked for a photograph

Answer: (c) Because hidden faults such as nicked insulation or a loose connection cannot be seen — a tidy-looking installation can still hide a dangerous fault that only a test will reveal.

Q8. Where are the measured test results for an installation recorded?

  • (a) On the cable drum
  • (b) On the back of the light switch
  • (c) In the installer’s notebook only
  • (d) On the test certificate and schedule of test results

Answer: (d) On the test certificate and schedule of test results — every measured value is written down so the installation can be proved safe and checked again later.

Q9. What is the likely result of energising an untested circuit that contains a live-to-earth fault?

  • (a) A shock or fire risk, or the protective device tripping at once
  • (b) The lights will simply be brighter
  • (c) Nothing at all will happen
  • (d) The meter will run backwards

Answer: (a) A shock or fire risk, or the protective device tripping at once — a live-to-earth fault puts voltage where it should not be, which is exactly what testing is meant to catch first.

Q10. Who should carry out the testing and commissioning of an installation?

  • (a) Anyone who owns a screwdriver
  • (b) A competent person who understands the tests, the instruments and the safe limits
  • (c) The person who delivers the materials
  • (d) The building owner, with no training

Answer: (b) A competent person who understands the tests, the instruments and the safe limits — wrong test settings or misread results can leave a dangerous installation looking safe.