NEC Code MCQs — Set 7
10 practice questions on NEC Article 690 solar photovoltaic systems — conductor sizing, rapid shutdown and disconnects.
Q1. Which NEC article covers solar photovoltaic (PV) systems?
- (a) Article 210
- (b) Article 430
- (c) Article 690
- (d) Article 705
Answer: (c) Article 690 — Article 690 covers solar PV systems, including PV source circuits, inverters and disconnects.
Q2. PV source-circuit conductors must be sized at what percentage of the PV module short-circuit current (Isc)?
- (a) 100%
- (b) 115%
- (c) 125%
- (d) 150%
Answer: (c) 125% — NEC 690.8 requires PV source-circuit conductors to be sized at 125% of the short-circuit current to allow for higher-than-rated sunlight conditions.
Q3. A PV module has a short-circuit current of 10 A. What is the minimum ampacity for its source-circuit conductors?
- (a) 10 A
- (b) 11.5 A
- (c) 12.5 A
- (d) 15 A
Answer: (c) 12.5 A — 10 A × 1.25 = 12.5 A per NEC 690.8.
Q4. What must rapid shutdown do to PV conductors on or in a building?
- (a) Increase their voltage
- (b) Reduce the voltage to 30 V or less within 30 seconds of initiation
- (c) Disconnect the battery only
- (d) Shut down the utility grid
Answer: (b) Reduce the voltage to 30 V or less within 30 seconds of initiation — NEC 690.12 rapid shutdown protects firefighters by de-energising PV conductors on a building.
Q5. What is the job of a solar inverter?
- (a) To store energy in batteries
- (b) To convert DC from the PV array into AC for the building and grid
- (c) To convert AC into DC for the panels
- (d) To step down the array voltage to 12 V
Answer: (b) To convert DC from the PV array into AC for the building and grid — PV modules produce DC, and the inverter makes it usable as household AC.
Q6. Is a disconnecting means required for a PV system?
- (a) No, PV systems never need a disconnect
- (b) Yes, a readily accessible disconnect is required for the PV system
- (c) Only for systems over 10 kW
- (d) Only for off-grid systems
Answer: (b) Yes, a readily accessible disconnect is required for the PV system — NEC 690.13 requires a disconnect so the system can be isolated for service and emergencies.
Q7. PV systems must have ground-fault protection. What is its purpose?
- (a) To increase power output
- (b) To detect a fault to ground and disconnect the array before a fire starts
- (c) To ground the inverter case only
- (d) To charge the battery faster
Answer: (b) To detect a fault to ground and disconnect the array before a fire starts — NEC 690.41 requires grounded PV systems to have ground-fault protection.
Q8. DC PV circuits on or in a dwelling must have what additional protection?
- (a) Surge protection only
- (b) Arc-fault circuit protection
- (c) Lightning rods
- (d) A second inverter
Answer: (b) Arc-fault circuit protection — NEC 690.11 requires PV DC circuits on dwellings to have arc-fault protection, because a DC arc can start a roof fire.
Q9. Where must the rapid shutdown initiation device be located?
- (a) On the roof next to the array
- (b) At a readily accessible location, such as the service equipment
- (c) Inside the inverter only
- (d) At the utility transformer
Answer: (b) At a readily accessible location, such as the service equipment — firefighters and service workers must be able to start rapid shutdown quickly without climbing onto the roof.
Q10. Must PV module frames and mounting rails be grounded or bonded?
- (a) No, they are not part of the electrical system
- (b) Yes, exposed metal parts of the array must be grounded or bonded
- (c) Only in commercial systems
- (d) Only if the array is over 600 V
Answer: (b) Yes, exposed metal parts of the array must be grounded or bonded — metal frames and rails must be bonded so a fault to the frame trips the protection instead of leaving the frame live.