Busbar MCQs — Set 5
10 practice questions on single and double busbar systems, bus couplers and sectionalised busbars.
Q1. What is the main drawback of a single busbar system?
- (a) It is the most expensive system
- (b) Any fault or maintenance on the busbar shuts down the whole supply
- (c) It cannot supply three-phase loads
- (d) It needs twice as many circuit breakers as a double busbar
Answer: (b) Any fault or maintenance on the busbar shuts down the whole supply — with only one bus, there is no alternative path, so the whole board must be switched off to work on it.
Q2. What is the main advantage of a double busbar system?
- (a) It uses less copper than a single busbar
- (b) One busbar can be taken out for maintenance while the other keeps supplying the load
- (c) It removes the need for circuit breakers
- (d) It doubles the voltage of the supply
Answer: (b) One busbar can be taken out for maintenance while the other keeps supplying the load — each feeder can be switched between the two buses, giving supply continuity during busbar work.
Q3. What is a bus coupler (bus-tie) breaker used for?
- (a) To connect or disconnect two busbar sections so load can be transferred between them
- (b) To measure the busbar voltage
- (c) To earth the busbar permanently
- (d) To convert AC to DC
Answer: (a) To connect or disconnect two busbar sections so load can be transferred between them — the coupler joins sections for normal running and opens to isolate a faulty or under-maintenance section.
Q4. Why is a long busbar divided into sections with a bus coupler between them?
- (a) To make the busbar longer
- (b) To limit the effect of a fault to one section and allow part of the plant to keep running
- (c) To increase the voltage
- (d) To remove the need for insulators
Answer: (b) To limit the effect of a fault to one section and allow part of the plant to keep running — sectionalising confines a bus fault to one part of the system instead of blacking out the whole board.
Q5. A three-phase load draws 200 kW at 400 V with a power factor of 0.85. What current must the incoming busbar carry?
- (a) 339.6 A
- (b) 250 A
- (c) 180.4 A
- (d) 400 A
Answer: (a) 339.6 A — I = P ÷ (√3 × V × pf) = 200,000 ÷ (1.732 × 400 × 0.85) = 200,000 ÷ 589 = 339.6 A.
Q6. Which busbar scheme would you choose for a hospital or other critical load that cannot tolerate a shutdown?
- (a) Single busbar, because it is simplest
- (b) Double busbar or sectionalised busbar with a coupler, for supply continuity
- (c) No busbar at all — direct cables only
- (d) A busbar with no circuit breakers
Answer: (b) Double busbar or sectionalised busbar with a coupler, for supply continuity — critical loads need an alternative supply path so one busbar outage does not cut the power.
Q7. What is a main-plus-transfer busbar scheme?
- (a) A scheme with a main bus for normal supply and a transfer bus that feeders can be switched to during maintenance
- (b) A scheme with two buses both carrying full load at all times
- (c) A scheme that transfers power between two countries
- (d) A scheme with no isolators at all
Answer: (a) A scheme with a main bus for normal supply and a transfer bus that feeders can be switched to during maintenance — the transfer bus is normally dead and is energised through a bus coupler when the main bus needs work.
Q8. What is the main cost of choosing a double busbar system over a single busbar?
- (a) It needs more copper, more isolators and more space, so it costs more and is more complex to operate
- (b) It costs less in every case
- (c) It needs no protection at all
- (d) It cannot be extended later
Answer: (a) It needs more copper, more isolators and more space, so it costs more and is more complex to operate — the extra bus, switches and interlocking buy reliability at a higher price.
Q9. In a double busbar system, what must an operator do before moving a feeder from one bus to the other?
- (a) Nothing — either bus can be used at any time
- (b) Follow the correct switching sequence with isolators and check interlocks, so the two buses are never wrongly paralleled or a load left unsupplied
- (c) Switch off the whole substation first
- (d) Remove the bus coupler permanently
Answer: (b) Follow the correct switching sequence with isolators and check interlocks, so the two buses are never wrongly paralleled or a load left unsupplied — bus transfer is a switching operation that needs the right order and interlock checks to stay safe.
Q10. What is the “one-and-a-half breaker” busbar scheme?
- (a) A scheme with three breakers for every two circuits, so any breaker can be maintained without losing a circuit
- (b) A scheme with one breaker shared by all circuits
- (c) A scheme that uses half a breaker per circuit
- (d) A scheme with no busbars at all
Answer: (a) A scheme with three breakers for every two circuits, so any breaker can be maintained without losing a circuit — the breaker-and-a-half arrangement is used at high-voltage substations where reliability matters most.
Also read: Breaker and Protection MCQs | All MCQ Topics