Busbar MCQs — Set 5

10 practice questions on single and double busbar systems, bus couplers and sectionalised busbars.

Q1. What is the main drawback of a single busbar system?

  • (a) It is the most expensive system
  • (b) Any fault or maintenance on the busbar shuts down the whole supply
  • (c) It cannot supply three-phase loads
  • (d) It needs twice as many circuit breakers as a double busbar

Answer: (b) Any fault or maintenance on the busbar shuts down the whole supply — with only one bus, there is no alternative path, so the whole board must be switched off to work on it.

Q2. What is the main advantage of a double busbar system?

  • (a) It uses less copper than a single busbar
  • (b) One busbar can be taken out for maintenance while the other keeps supplying the load
  • (c) It removes the need for circuit breakers
  • (d) It doubles the voltage of the supply

Answer: (b) One busbar can be taken out for maintenance while the other keeps supplying the load — each feeder can be switched between the two buses, giving supply continuity during busbar work.

Q3. What is a bus coupler (bus-tie) breaker used for?

  • (a) To connect or disconnect two busbar sections so load can be transferred between them
  • (b) To measure the busbar voltage
  • (c) To earth the busbar permanently
  • (d) To convert AC to DC

Answer: (a) To connect or disconnect two busbar sections so load can be transferred between them — the coupler joins sections for normal running and opens to isolate a faulty or under-maintenance section.

Q4. Why is a long busbar divided into sections with a bus coupler between them?

  • (a) To make the busbar longer
  • (b) To limit the effect of a fault to one section and allow part of the plant to keep running
  • (c) To increase the voltage
  • (d) To remove the need for insulators

Answer: (b) To limit the effect of a fault to one section and allow part of the plant to keep running — sectionalising confines a bus fault to one part of the system instead of blacking out the whole board.

Q5. A three-phase load draws 200 kW at 400 V with a power factor of 0.85. What current must the incoming busbar carry?

  • (a) 339.6 A
  • (b) 250 A
  • (c) 180.4 A
  • (d) 400 A

Answer: (a) 339.6 A — I = P ÷ (√3 × V × pf) = 200,000 ÷ (1.732 × 400 × 0.85) = 200,000 ÷ 589 = 339.6 A.

Q6. Which busbar scheme would you choose for a hospital or other critical load that cannot tolerate a shutdown?

  • (a) Single busbar, because it is simplest
  • (b) Double busbar or sectionalised busbar with a coupler, for supply continuity
  • (c) No busbar at all — direct cables only
  • (d) A busbar with no circuit breakers

Answer: (b) Double busbar or sectionalised busbar with a coupler, for supply continuity — critical loads need an alternative supply path so one busbar outage does not cut the power.

Q7. What is a main-plus-transfer busbar scheme?

  • (a) A scheme with a main bus for normal supply and a transfer bus that feeders can be switched to during maintenance
  • (b) A scheme with two buses both carrying full load at all times
  • (c) A scheme that transfers power between two countries
  • (d) A scheme with no isolators at all

Answer: (a) A scheme with a main bus for normal supply and a transfer bus that feeders can be switched to during maintenance — the transfer bus is normally dead and is energised through a bus coupler when the main bus needs work.

Q8. What is the main cost of choosing a double busbar system over a single busbar?

  • (a) It needs more copper, more isolators and more space, so it costs more and is more complex to operate
  • (b) It costs less in every case
  • (c) It needs no protection at all
  • (d) It cannot be extended later

Answer: (a) It needs more copper, more isolators and more space, so it costs more and is more complex to operate — the extra bus, switches and interlocking buy reliability at a higher price.

Q9. In a double busbar system, what must an operator do before moving a feeder from one bus to the other?

  • (a) Nothing — either bus can be used at any time
  • (b) Follow the correct switching sequence with isolators and check interlocks, so the two buses are never wrongly paralleled or a load left unsupplied
  • (c) Switch off the whole substation first
  • (d) Remove the bus coupler permanently

Answer: (b) Follow the correct switching sequence with isolators and check interlocks, so the two buses are never wrongly paralleled or a load left unsupplied — bus transfer is a switching operation that needs the right order and interlock checks to stay safe.

Q10. What is the “one-and-a-half breaker” busbar scheme?

  • (a) A scheme with three breakers for every two circuits, so any breaker can be maintained without losing a circuit
  • (b) A scheme with one breaker shared by all circuits
  • (c) A scheme that uses half a breaker per circuit
  • (d) A scheme with no busbars at all

Answer: (a) A scheme with three breakers for every two circuits, so any breaker can be maintained without losing a circuit — the breaker-and-a-half arrangement is used at high-voltage substations where reliability matters most.